What’s the latest on your top assembly? I got notified mine was going into powder coat last Thursday so I’m sort of gauging my timeline off of what you’ve written since yours seems to be a batch or 2 ahead of mine.After the agonizing 2 year experience with ADV and the 90 day wait of getting my refund I am finally close to getting my Armadillo HT. Below is the timeline of my order to give an idea to those who have recently ordered, or in the same batch or still thinking of ordering. I will say Fabian has been 100% transparent and truthful about any delays to the whole process. Also since the time of my order there have been many improvements in the manufacturing process including access to a much larger powder coating facility which will help them de-bottleneck this constraint.
9/20/24 - Order #413 Placed (Black Slantback) - week 0
11/18/24 - Cutting and Bending (must have just missed the previous batch) - 8.5 wks after order
1/13/25 - Welding and Blending - 16.5 wks after order
3/20/25 - Powder Coating (currently taking 4 to 6 wks) - 25.5 wks after order
4/17 to 5/1 (est) - Assembly and QC - 29.5 to 31.5 wks after order
4/24 to 5/8 (est) - Crating and Shipment - 30.5 to 32.5 wks after order
Based on the information that Fabian has shared in social media and me chatting with him I would guess that 20 week delivery is what they can probably do if order is placed today. Which is reasonable considering this is mostly a custom hand made product of high quality(based on feedback from those who have taken delivery). I will try to avoid getting too excited until it shows up in my driveway but it sure is getting close.