  1. OFFICIALLY UNDERWAY: Phase 1 Mass Production of the 2021 Bronco! [Updated With Units Produced Daily]

    Two shifts per day, and I believe they are planning Saturdays on a two on / one off rotation once they reach full production speed.
  2. Duplicate "Your Bronco order has been confirmed" email

    This was my thought but surely more would be getting them?
  3. Duplicate "Your Bronco order has been confirmed" email

    My order confirmation email came on 1/20/21, but just now I received a duplicate "your order has been confirmed" email. No changes in my account and the details all still look right. Did anyone else receive an email this evening? I'm curious as to if numbers are starting to get queued up.
  4. Bronco's Appearing in Ford's Dealer to Dealer Location Tool

    My wife says the exact same thing... 🤷‍♂️
  5. Bronco's Appearing in Ford's Dealer to Dealer Location Tool

    Intentionally a bit vague- IF a converted reservation is assigned a VIN and scheduled for production prior to Job1, the customer is not likely to be notified of its status until 1) That build batch is complete with satisfactory inspections, and 2) OKTB is issued overall. So, on or around 5/3...
  6. OFFICIALLY UNDERWAY: Phase 1 Mass Production of the 2021 Bronco! [Updated With Units Produced Daily]

    Without being too specific, damage from manually-operated assisted machining.
  7. OFFICIALLY UNDERWAY: Phase 1 Mass Production of the 2021 Bronco! [Updated With Units Produced Daily]

    Published Job 1 won't change. If things continue so go smoothly, dealers should check their demo build schedules over the next few weeks.
  8. OFFICIALLY UNDERWAY: Phase 1 Mass Production of the 2021 Bronco! [Updated With Units Produced Daily]

    It's literally the 3rd day of ramp up and a month ahead of Job 1. These numbers are great, especially with only one scrap.
  9. OFFICIALLY UNDERWAY: Phase 1 Mass Production of the 2021 Bronco! [Updated With Units Produced Daily]

    10 units Tuesday, 16 yesterday, 25 today. Only one scrap needed thus far, which is remarkable for a new unit with all new tooling. It's quite possible that the MP2 phase will be skipped and they'll ramp straight thru MP1 to Job 1.
  10. OFFICIALLY UNDERWAY: Phase 1 Mass Production of the 2021 Bronco! [Updated With Units Produced Daily]

    Pop the corks! After a commodity shortage delayed yesterday's planned start, Bronco officially entered Phase 1 Mass Production at 8:30 a.m. today. These early builds will be used for press rides and dealer demos, and the official Job 1 date remains unchanged as 5/3, legally sellable, VIN...
  11. Is tomorrow job 1? Should it be a bronco6g holiday?

    Not at all. The MP1 phase was always meant to be a batch / stop / inspect scenario, I believe starting with 500 units. Getting delayed 2 days (from today to Wednesday) won't impact things at all. Now, if these commodity issues continue...
  12. Is tomorrow job 1? Should it be a bronco6g holiday?

    Phase one Mass Production has been delayed to Wednesday, March 31st, as the plant awaits parts. Womp womp.
  13. What is the "Production" Process that begins on March 29th?

    All correct above. An interesting tidbid... there was a change made to the floor welds made prior to the 2/19 final Federal certification. Can't speak to the implication, but this was pretty late-stage to make an adjustment like that. Legally speaking, anything produced after 2/19 can be...
  14. Any update on the start of Job 1?

    Production plan hasn't changed from what was locked in a few weeks ago: Mass Production Phase 1 begins 3/29 with a run of 500. There will be a series of runs, stops, and inspections throughout April. The plant expects to be at launch speed (not full speed) prior to the 5/3 Job1 date.
  15. This is not a cup holder!

    We have 12, 11, and 2 year old girls, a 9 year old boy, an 11 year old 115lb Golden Retriever mix and a 6 month old Border Collie. Never a dull (or clean) moment around her.