I was actually at the dealer today because my parents just bought a new escape and we pulled the order sheet.
These are all my build dates.
7/26, 8/23, 8/30, 9/27 ,10/18, 10/25, 11/08
I’m seriously hoping 11/08 is the last one.
I am a fairly early reservation holder with an order date of...
08/23 to 9/27 to 10/18 to 10/25 and as of today now 11/08.
2 Dr OBX w/trailer
My dealer had a bunch moved to 11/08 today. I was kidding about Christmas in my sig but damn looks like this may be a reality.
Same boat.
2dr OBX 2.7 Trailer Tow.
My Dates are similar to yours except my latest is 10/25 now.
I'm pretty sure they will get built.
I figure we waited this long whats another 45 days or so.
OBX 2dr Scheduled for 10/25 and a 11/01 delivery date.
4th times a charm right? Right?
I still feel any Vin'd hardtop scheduled for late Oct is going to be pushed back until Nov. Time will tell but after 226 days and 4 build dates my optimism is dwindling.
New guy here.
I just spent an hour clicking on all the links provided in the first post.
Wow did I miss a lot of good information that was never provided to my dealer.
Sometimes I feel like living in Canada we are a Third World country when it comes to information from Ford but reading all...
I have a Vin although no window sticker available yet.
build 08/23 and delivery 08/29.
im only 2 hrs from where they are built.
So far it hasn’t moved since the date was issued early July.